Construction schedule S-Curve and earned value management dashboard
Use Case — PMO & Project Controls

2,400 projects. 14 countries. One PMO team still working in Excel.

This is the real scenario most multinational EPC contractors are in today. The fix isn't more spreadsheets — it's a live control layer that connects field progress to executive reporting automatically.

See how it works
The scenario

A familiar story in large-scale construction

A multinational infrastructure contractor manages 2,400 active projects across Latin America, Europe, and the Middle East. Their central PMO has 14 analysts. Every month, each project manager submits a schedule update — a PDF report built from an Excel file with their own column headers, their own WBS structure, and their own definition of "% complete."

The PMO consolidates everything manually. Copying numbers. Reformatting tabs. Chasing project managers for corrections. The process takes three weeks. By the time the SPI dashboard is ready for the board presentation, the data is already six weeks old.

Meanwhile, a road project in Colombia had an SPI of 0.71 in week 8 — a clear schedule risk signal. Nobody in HQ saw it until the week-14 report. The delay had already cascaded into a contractual penalty.

"We had the data. It was somewhere in 2,400 Excel files on a SharePoint that nobody had organized. The problem wasn't information — it was that we couldn't see any of it in real time."

PMO Director, Infrastructure & Civil Works

What changes when field progress drives reporting automatically

Before

Without Construway

  • SPI is calculated once a month, manually, after the PMO team spends 3 weeks normalizing Excel files from 2,400 project managers.

  • Each PM defines "% complete" differently — hours spent, tasks ticked, area inspected. There is no consistent metric across the portfolio.

  • S-curves are built in PowerPoint for each board presentation. Any project with an SPI below 0.80 is discovered weeks after the risk became critical.

  • Risk flags live in email threads and individual spreadsheets. The PMO has no aggregated view of which projects are in distress at any given moment.

After

With Construway

  • SPI is recalculated every time a field engineer updates task progress — from any device, at any site. The PMO sees it live, without waiting for month-end submissions.

  • % complete is calculated from duration-weighted leaf-node progress in the WBS — not from subjective estimates. Every project uses the same engine.

  • S-curves are generated automatically. The Colombia road project's SPI drop to 0.71 would have surfaced at week 8 — giving the team 6 weeks to act before the contractual deadline.

  • The PMO dashboard shows all active projects ranked by SPI. Projects below threshold are flagged automatically. Analysts spend time on mitigation, not on data collection.

The control layer your PMO has been missing

Each capability below maps directly to a manual process that large EPC PMO teams do today — and that Construway eliminates.

Standardized WBS across all projects

Every project uses the same tree-based WBS structure. Eliminates the "each PM uses their own columns" problem — progress data is comparable and aggregatable across the entire portfolio.

Live SPI & CPI — no month-end wait

Schedule Performance Index and Cost Performance Index are recalculated from field updates in real time. The 3-week consolidation process becomes a live feed. The Colombia slippage scenario gets caught in week 8, not week 14.

Automatic S-curves — no PowerPoint

Planned vs. Actual S-curves are generated automatically from the schedule and field progress data. Board presentations use live charts, not manually assembled slides built the night before.

Portfolio risk dashboard

Projects below SPI threshold are flagged automatically. The PMO sees the full portfolio ranked by performance — without opening a single Excel file or asking a single project manager for a status update.

MS Project

You already have the schedules. Connect them.

Most large contractors already manage baselines in MS Project. Construway doesn't replace those tools — it imports files and syncs field updates back to the master schedule. Your planners keep their tool. Your PMO gets live visibility.

globe
CTA

Ready to connect your projects and site logistics?

Start with a walkthrough focused on your active projects, approval flow, and delivery bottlenecks. Join the leading construction teams optimizing their workflows today.