April 2026

New PMO Field Apr 12, 2026

Company-level weather activity exclusions

Companies can now opt out of specific weather activity types that don't apply to their operations. A contractor in an arid region can disable precipitation rules for outdoor work without affecting other alert categories. Exclusions are scoped per company and never bleed into other tenants' configurations.

Improved PMO Apr 12, 2026

Weather alerts now surface critical path exposure

Weather alerts are now enriched with critical path context. When a weather-sensitive task sits on the critical path, its alert is automatically elevated in severity. The critical path impact summary shows estimated delay days and the count of tasks at risk — giving PMO teams actionable data before a weather event hits.

February 2026

New Field Admin Feb 25, 2026

Logistics subscription tiers

The Logistics module now enforces usage limits per billing period across four tiers: Starter, Growth, Operations Pro, and Enterprise. Request usage is tracked per company and resets each period. Current usage and remaining quota are visible in the dashboard — there are no automated notifications; admins are expected to monitor usage there.

Improved Field Admin Feb 15, 2026

Material catalog scoped per company

The material catalog is now fully isolated per company. Each organization manages its own material list with independent codes, units, and descriptions. No material from one tenant is ever visible to another — consistent with the platform-wide data isolation model.

Improved Field Feb 14, 2026

Sequential request IDs scoped per company

Material requests now carry a company-scoped sequential number (e.g. MRQ-001, MRQ-002) in addition to their internal UUID. Makes requests easy to reference in site conversations and email without exposing platform-level identifiers.

Improved Field PMO Feb 9, 2026

Logistics request statuses expanded

Material requests now flow through five named statuses: Pending, Scheduled, In Progress, Completed, and Cancelled. Each transition is timestamped. The full lifecycle history is visible to the requesting engineer, the warehouse team, and the PMO.

New Field PMO Admin Feb 2, 2026

Logistics module launched

The Logistics & Materials module is now available. Field engineers submit structured material requests linked to a usage date and time. Requests flow through a configurable approval and separation workflow with a company-level cutoff time. Unplanned requests require written justification and are flagged as urgent. The warehouse sees a demand calendar. The PMO sees SLA compliance metrics.

New Admin Feb 2, 2026

Multi-factor authentication

MFA is now enforced across all user accounts using TOTP-based authenticator apps. Each login requires an independent verification step.

December 2025

New PMO Dec 10, 2025

Critical path flag on schedule tasks

Tasks imported from MS Project now carry their critical path flag into Construway. When a task is marked critical in the source file, the flag is preserved on import. Available in schedule views for filtering. Only applies to schedules imported via MS Project XML — tasks created manually in the task tree do not carry this flag.

Improved PMO Dec 30, 2025

WBS import improvements for MS Project

Schedule import handling was improved for WBS structures exported from MS Project. Parent-child relationships, outline codes, and percent-planned overrides now import correctly from external baseline files.

September 2025

New PMO Admin Sep 14, 2025

Submittals module launched

Submittals are now managed within Construway. Documents are grouped into packages and reviewed through a structured approval workflow. Every review cycle is recorded with reviewer identity and timestamp. Each submittal carries its full revision history.

Improved PMO Sep 1, 2025

Schedule: external baseline import via status dates

Status dates can now be flagged as imported, allowing percent-planned values to be sourced from an external baseline (e.g. MS Project export) rather than recalculated internally. Teams that manage baselines externally can still generate SPI and S-curves inside Construway without re-entering their plan.

February 2025

New Field PMO Admin Feb 16, 2025

Platform launched — Schedule, Risk, Punch List, Photo Reports

Initial production release. Ships with: WBS-based Schedule & EVM with duration-weighted S-curves and live SPI; Risk management with probability-impact matrix and automatic risk score calculation; Punch List with photo attachments, priority, and status tracking; Photo Reports with date ranges and tagged detail entries. All modules share company-level data isolation and project-level role permissions.